Denton Proposed South Library

 

 
 

PROJECT DESCRIPTION

Very conceptual cost information for several options, including new vs. renovation, were essential for stakeholders. PPV delivered these tools in 2020, as well as again in 2022/2023.

PPV’s first effort in 2020 was helpful to the City team in evaluating site and other project options, and reaching consensus on next steps. We are ready to move forward with delivering best value for this important community asset.


PROJECT DETAILS

SIZE: 40,000 SF
BUDGET: $62.3 Million
OWNER: City of Denton, TX
ARCHITECT: TBD
CONTRACTOR: TBD
COMPLETION DATE: TBD; NOV 2023 Bond Project

 

UNIQUE PROJECT CHALLENGES

  • Provide solid cost data for decision-makers for very different facility options.

  • Use minimal conceptual designs & PPV cost models to finalize scope.

  • Summarize complex results for team; project cost escalation in volatile market.