Richardson City Hall & Civic Center Renovation Options


 

PROJECT DESCRIPTION

The combination of options available for the City Hall and Civic Center were complex, as each use could benefit from a renovation, expansion or building a new facility.

When the two facility programs were combined with the construction alternatives, the analysis became very complicated. PPV helped generate clarity here.


PROJECT DETAILS

SIZE: 95,000 SF
BUDGET: $100 Million approx.
OWNER: City of Richardson, TX
ARCHITECT: Architexas Design Group
CONTRACTOR: Not Applicable 
COMPLETION DATE: Q4, 2025

 

UNIQUE PROJECT CHALLENGES

  • Provide solid cost data for decision-makers for very different facility options.

  • Use minimal conceptual designs.

  • Dovetail with previous Library cost models, with no over-laps or gaps.

  • Present cost info for very complex options in useful format.